EnergiAcres
Capex $0.00M

EAOS-North Central

700 AC
⚡ 2.8 mi · 🔥 3.3 mi · 💧 4.1 mi · ⚠️ 2 Bores
Interconnect Route Mode Road corridor routing with highway bore analysis

Utility Interconnect Matrix

12.4 mi total
⚡

Electric Transmission

South Canton Substation
$6.56M
Distance 2.8 mi
Voltage 138 kV
Capacity 1000 MVA
HDD Bores 1 Crossings
🔥

Natural Gas Pipeline

Rover Pipeline Lateral
$5.13M
Distance 3.3 mi
Diameter 42"
Pressure 1440 PSI
HDD Bores 1 Crossings
💧

Water & Industrial Sewer

County Main Line
$3.82M
Distance 4.1 mi
Diameter 24"
Surplus 5.0 MGD
HDD Bores 0 Crossings
🌐

Diverse Dark Fiber

Zayo Long Haul
$1.48M
Distance 2.2 mi
Strands 864 Count
Diversity Dual Path
HDD Bores 0 Crossings

Site Diligence & Parcel Data

Location Carroll County, OH
Coordinates -81.1245, 40.5732
Zoning Heavy Industrial (I-2)
IRA § 48 Energy Community Eligible (+10% Adder)
PJM Interconnection Queue Cluster 1 · DLS Ready
Launch Desktop CAD Workspace